Case Study

Catarman Bridge Widening

DPWH Region VIII · Catarman–Laoang Road, Northern Samar

₱141M
Contract Value
300
Calendar Days
Apr 2019
Opened to Public
The Brief

Widening a vital river crossing

The Catarman Bridge carries the Catarman–Laoang Road across the river at the heart of Northern Samar's provincial capital — a route used daily by commuters, farm-to-market traffic, and inter-municipal transport. DPWH Region VIII commissioned the widening to add capacity along this corridor. CTC Construction and Supplies delivered the works as part of a joint venture, from substructure through to final road tie-in.

Scope of Work

What the project covered

  • Pile driving and substructure works for the widened span
  • Superstructure widening and deck concreting
  • Road tie-in and pavement works at both approaches
  • Delivered under a joint-venture arrangement with DPWH Region VIII
Before & After

From substructure to opening day

Catarman Bridge during pile driving and substructure works
During construction — pile driving and substructure works.
Completed Catarman Bridge widened span
Completed — opened to the public, April 2019.
Process

How it came together

1

Mobilization

Site setup and joint-venture mobilization along the Catarman–Laoang Road.

2

Substructure

Pile driving and foundation works for the widened span.

3

Widening & Finishing

Deck widening, concreting, and road tie-in at both approaches.

4

Turnover

Completed within 300 calendar days and opened to traffic, April 2019.